Import MS Project XML file

This popup form is used to load a new/updated schedule into Psoda from a MS Project XML file. If you have a normal MS Project file then you have to open that file in MS Project first and save it as an XML file. The import process has a number of phases:

Phase 1 – Select file and import options

The first phase is to select the file to import and set the options. The form will have the following fields:
Location: This read-only field shows the location you selected to import the file.
MS Project XML file*: You must select the XML file that you want to import. The file must be less than 8MBytes. If you have a large file you can either zip or gzip the file before uploading to Psoda.
Mark all tasks as advanced estimates?: If you MS Project file contains tasks with time-phased estimates then set this checkbox so that all the imported tasks use the Advanced Estimates setting in Psoda.
Import start/end dates?: If you set this checkbox then the start/end dates from your MS Project file will be used as fixed start/end dates in Psoda.
If you already have a task group in your programme/project then you will get some additional options in this form:
Update WBS or Task group: Use this drop-down to select an existing WBS/Task group to update instead of creating a new WBS/Task group. If you do want to create a new WBS/Task group select the None option.
Baseline WBS before update: Set this checkbox if you want to baseline the selected WBS/Task group first before loading the new MS Project file.
*The MS Project XML file field is the only mandatory field, all the others are optional.

Phase 2 – Resource mapping

During this step you get the opportunity to map the resources from your MS Project file to Psoda roles and/or users. If the corresponding role/user does not exist in Psoda you can use the options to add new roles/users. These options will only be available if you have permissions to add roles/users. If you do not want to proceed with the import then this is the last opportunity to “Cancel”.

Phase 3 – Import

During this phase the MS Project is imported into Psoda. You will see a progress indicator. Once the import is finished the button at the bottom of the form will change to Next.

Phase 4 – Results

The final phase shows you the results of the import.