This popup form is used to recalculate the critical path for the selected
programme,
project or
task group.
Before the critical path is recalculated the critical flags for all of the
tasks and
milestones of the selected asset are reset.
The critical path is calculated by:
- Find all of the tasks/milestones with the latest end dates
- Follow all of the predecessor links where the gap is less than 1 hour
- If there are no predecessor links with gaps less than one hour then this becomes the starting point of a possible critical path
- From all of the possible critical paths select those with the earliest start date
- Mark all of the tasks/milestones along the critical path