Edit task form

You may edit some aspects of the chosen milestone using inline editing, or you may utilise the edit popup described below. This popup form can be accessed via the Edit button iconedit button in the top header area of the task view page, as shown in Figure 1. Alternatively you can access the Edit iconedit popup form via the Actions menu iconactions column menu of the Schedule table at any of the parent asset view pages (e.g. Contact details iconorganisation, Programme iconprogramme, Project iconproject, Subproject iconsub-project, working task grouptask group or Change requests iconchange request), as shown in Figure 2.

Figure 1 – Access via edit button 

Figure 2 – Access via tasks& milestones tab

  This popup is shown in Figure 3 and is used to edit an existing task.

Figure 3 – Edit task form

In Figure 3 above, the form has been broken down into three sections:

Section 1 This section contains a selection of important top fields: Parent assets: This read-only field shows which organisation, programme, project, sub-project and/or lower level this task resides under. This provides a breakdown of the asset hierarchy so that you can see how many levels down this task is in Psoda. Reference*: This is a mandatory field where a unique reference for this task must be entered. NOTE: if this reference is changed, it must remain unique across the whole of the parent asset. Renumber existing tasks & milestones: Select this check box if you want to insert this task and renumber any existing task groups, tasks or milestones. Wait for update to complete: If this task has dependant tasks/milestones then it may take a while to complete the update and propagate it to all of the dependants. Select this check box to get a progress indicator to show how the update is progressing. If you de-select this checkbox then the update will happen in the background and you will not be able to track how it is progressing.
Section 2 These are the tabs that you can cycle through to edit each section of the task.When you navigate to a new tabbed view in this popup, any information entered in Section 3 from the previous tabbed view will be saved. This means you do not need to click on any buttons to save each tab, but can instead click on the Update button at the bottom of the popup when you wish to update this task with the set details.
Section 3 This information will change as you cycle through the tabs shown in Section 2, and the available fields will change accordingly. A breakdown of the field information for each tab is provided below.

Tab breakdown

The following information provides a breakdown of each of the tabbed views that may be available for you to adjust the task’s details under each section.

Task map iconDetails

Figure 4 – Edit task details tab

The details for the task can be assigned or adjusted by clicking on the tab indicated in Figure 4 above. Each of the fields available to be customised in this tabbed view are described in the following table:
Category*: Use this drop-down to change the category for this task.
(Add a new category): This field will only be available if you have selected the “Add new category” option in the Category field above. Use this field to enter a new category for this task.
Title: Enter or edit the short title for this task here.
Description: Enter or edit the longer description for this task here.
Job code: Enter or edit the job code for this task here. If you have set a job code prefix for your programme then the Reference iconnext available job code will automatically be calculated.
General Ledger Number: Enter or edit the GL number for this task here.
Deliverable: Select this check box if you want this task to represent a deliverable.
Core R&D Activity: Select this check box if you want this task to be part of your core R&D activity for tax purposes.
Supporting R&D Activity: Select this check box if you want this task to be part of your Supporting R&D activity for tax purposes.
Approved: Select this check box if this task has been approved and is available to resources to add to their Timesheets icontimesheets.
Archived: Select this check box if you want to set this task as archived so that it is no longer available to resources to add to their timesheets.

gantt Planning

Figure 5 -Edit task planning tab

Critical: Select this check box if you wish to mark this task as part of a critical pathway.
Estimate type: Select or change whether this task is a fixed effort or fixed duration task. If you select Fixed effort then Psoda will calculate the duration for based on the allocation levels. If you select Fixed duration then Psoda will calculate the required effort based on the allocation levels. If you select Advanced estimates then the start date, end date and estimate fields will be hidden, and you can come back and edit these estimates after this task has been created.
Start date: Enter or edit the earliest start date for this task using one of the supported date formats or by selecting the desired date using choose date iconcalendar control. If the task has predecessors that may push the task to a later start date.
End date: Enter or edit the latest end date for this task using one of the supported date formats or by selecting the desired date using choose date iconcalendar control. If the task has predecessors that may push the end date earlier.
(Estimated duration): This field will be visible if you selected the “Fixed duration” option in the Estimate type field above. Enter or edit the estimated duration for this task as a number of 8 hour days. For example 1.5 will be 8 + 4 hours. You can also use 1:30 or 1h 30m.
(Estimated effort): This field will be visible if you selected the “Fixed effort” option in the Estimate type field above. Enter  or edit the estimated effort for this task as a number of 8 hour days, for example 1.5 or 1:30 or 1h 30m.
Priority: Enter or edit the priority for this task as a number from 0 to 1000000.
Actual effort: Enter the actual effort that has been spent working towards completing this task as a number of 8 hour days.
Estimated effort to complete: Enter the estimated effort required to complete this task as a number of 8 hours days. If you leave this field blank then Psoda will estimate the effort based on actual effort and % complete.
Estimated progress: Enter or edit the estimated progress for this task as percentage. 0% means the task has not been started and 100% means the task has been completed. If you leave this field blank then Psoda will estimate the progress based on the estimated effort, the actual effort and the estimated effort to complete the task.
Charge model: This field will only be visible if you have sufficient permissions.Use the drop-down list to select or change the charge model for this task. The following options are available:
  • Non-billable – not billable or chargeable
  • Once-off – charged once as a fixed cost
  • Hourly – charged on an hourly rate
  • Daily – charged on a daily rate
  • Sick leave – leave time against this task will be deducted from the user’s available sick leave.
  • Annual leave – leave time against this task will be deducted from the user’s available annual leave.
Charge rounding: This field will only be visible if you have sufficient permissions.Use the drop-down list to select or change how timesheets will round the charges for this task. The following options are available:
  • None – no rounding will take place
  • Half-hour – rounding to the closest half-hour
  • Hour – rounding to the closest hour
  • Half-day (4 hours) – rounding to the closest half-day (or 4 hours)
  • Day (8 hours) – rounding to the closest day (or 8 hours)
Rate override: Fill in a new rate in this field if you want to override the role/individual rates.

Group icon Allocated to

Figure 6 – Add task allocated to tab

You can assign or adjust which users this task is allocated to by clicking on the tab indicated in Figure 6 above. Select the users you want to allocate this task to from the Not allocated to list. You may select multiple users or roles by holding the CTRL or SHIFT keys and clicking on the name of the additional user(s). To de-select, click on the highlighted name while still holding the CTRL or SHIFT keys so as not to lose all other selected users. Once you are happy with your selection, click on the down arrow to transfer these users to the Allocated to list. You may edit the users who are allocated to this task by shifting the users between the allocated and unallocated lists using the down and up arrows. The users who belong in the allocated list will be able to log expense items on their timesheets against this task.

Group icon Allocation levels

Add task allocation levels tab

This tab allows you to set or change the allocation levels for each of the users you selected on the Allocated to tab. Figure 8 provides a short example of this. For example if you set the allocation level to 50% for a particular user it means that 50% of that user’s time is allocated to this task for the duration of the task.   Once you are happy with your entries click the “Update task” button at the bottom of the form. This will update the task with the details that you supplied. It may take a little while to complete the task if it has a large number of links so the update will be completed in the background and show a progress bar (if you have selected the wait check box at the very top of this popup). Click the “Cancel” button if you no longer want to update the task.