The Budgets module can be used to keep track of
budget details for a particular
programme,
project,
sub-project or
change request. This includes budget baselines per month,
budget items and groupings and also actual costs.The budget is dependent on two attributes of the parent
asset:
Start date | If the asset start date is set then the month intervals for the budget will be based on that start date. |
---|
Budget intervals | The number of months allowed in the budget is set using this asset attribute. |
---|
A budget can have multiple
budget items. Each
budget item contains the baselines of costs for that item.
Budget items can be grouped into sub-groups of the budget, down to as many levels as is required. The baselines from the items are summed into the sub-group; and ultimately into the budget.An
asset can have multiple budgets, e.g. different version during the planning phase. The budgets are treated independently and are not summed together. If a budget is no longer required it may be archived if a history needs to be maintained or deleted if no history is required.A
workflow can also be selected for each budget. When you
add the budget you can select the
Standard Budget Workflow, or you can
add a new workflow for budgets specific to your
organisation.